DCMA 14H AND 14B CROSS DIKE AND WEIR IMPROVEMENTS, SAVANNAH, GA

DMCA 14H & 14B SAVANNAH, GA W912DS-18-C-0013 BRIEF DESCRIPTION Savannah Harbor Dredge Material Containment Area (DMCA) 14A will be used primarily for storage of the naturally occurring cadmium containing materials that will be excavated during Deeping of the Savannah River. Construction three water control weir structures within the DMCA 14A/14B cross dike, the addition of […]

FIRE ISLAND STABILIZATION – BAYSHORE, NY

FIRE ISLAND STABILIZATION BAYSHORE, NY W912DS-18-C-0017 BRIEF DESCRIPTION The entire project includes 19 miles of beach from Robert Moses State Park on the west end of the island, to Smith County Park at the east end and includes removal and placement of approximately 1 million cubic yards of material along the Long Island coastline. TITAN […]

STORM DAMAGER REDUCTION – BREVARD CO., FL

STORM DAMAGER REDUCTION BREVARD CO., FL Previous slide Next slide BRIEF DESCRIPTION This U.S. Army Corps of Engineers project was to construct artificial mitigation reef mats at ten sites from Satellite Beach to Indialantic in Brevard County. The low-lying reefs are concrete mats topped with coquina limestone. The plan was to construct ten reef sites […]

SHORE PROTECTION PROJECT – TREASURE ISLAND, FL

SHORE PROTECTION PROJECT TREASURE ISLAND, FL W912EP-13-D-0010 Play Previous Next BRIEF DESCRIPTION Norfolk Dredging was awarded the Beach Renourishment project last September of 2015. Originally Sunshine and Sunset beaches were to be filled first with sand dredged from John’s Pass. However, Norfolk Dredging changed the schedule in the order in which it was going to […]

CLOUTER CREEK DISPOSAL AREA DIKE CONSTRUCTION, CHARLESTON

DIKE RAISING CHARLESTON, SC W912HP-16-C-0010 BRIEF DESCRIPTION The work consists of furnishing all plant, equipment, labor, transportation, fuel, lubricant, supplies and materials; and performing all operations in connection with raising dikes and berms, installation of geotextile, and installation of new spillway systems in Clouter Creek Disposal Area – Middle Cell and repairing dikes and berms, […]

C-111 DETENTION AREA CONTRACT 8A – MIAMI, FL

C-111 DETENTION AREA CONTRACT 8A MIAMI, FL W912EP-16-C-0023 BRIEF DESCRIPTION The C-111, Contract 8A project features consist of the construction of internal flowway berms with weirs, modification of an existing levee and concrete weir, and a levee section crossing with associated roadway improvements. Work also includes clearing, grubbing, stripping, scraping, grassing, and environmental monitoring. The […]

DMCA DIKE RAISING WEIR IMPROVEMENTS, SAVANNAH

DIKE RAISING SAVANNAH, GA W912HN-12-D-0029 BRIEF DESCRIPTION This project includes the raising of the existing perimeter containment dike of the Dredge Material Containment Area (DMCA) 14B. The perimeter dike spans a length of 25,000 feet. The crest of the quote mark front dike, quote mark or the stretch of dike that parallels the Savannah River, […]

HERBERT DIKE REHAB STRUCTURE REPLACEMENTS C-10 C-12, OKEECHOBEE, FL

DIKE REHABILITATION MIAMI, FL W912EP-13-C-0027 BRIEF DESCRIPTION This project consisted of the replacement of existing dike culverts 5 and 5A on Lake Okeechobee. Culverts were replaced with a triple 10 x 10 cast in place concrete box with a liner pipe. Construction activities included: construction of a surcharge mound, demolition and removal of existing structures, […]

STONE REVETMENT – HULL, MA

STONE REVETMENT HULL, MA W912WJ-18-C-0007 Previous slide Next slide BRIEF DESCRIPTION The work of this project involves the construction of an armor stone revetment at Nantasket Beach in Hull, Massachusetts. The armor stone and related materials shall be placed in front of an existing concrete seawall along a 2,200 linear foot continuous length. Large cut […]

MAGNA VISTA LEVEES – BRUNSWICK, MS

MAGNA VISTA LEVEES BRUNSWICK, MS W912EE-15-C-0012 Previous slide Next slide BRIEF DESCRIPTION Clearing and grubbing, excavation, levee construction and compaction, berm embankment uncompacted, construction ramps and entrances, demolition, removal of existing pavement and granular base course, cattle guard installation, existing levee resurfacing, installation of relief wells, existing turf maintenance and new turf establishment, erosion control […]